Featured Projects - Interstate - 84 and 95 Connecticut

Back to Featured Projects

The Challenge


Evaluate the risk and mitigate cost damages to St. Paul / Travelers on two high profile DOT highway projects on which a well-established highway contractor was terminated with over 30 million dollars of work remaining.

The GCS Solution


GCS promptly assembled a team of experienced personnel to accurately forecast the cost and schedule of each project, proposed alternate solutions to reduce risk exposure, prepared new documents for bidding purposes while concurrently evaluating an independent cost proposal from a qualified contractor.

The Result


A "risk sharing" contract was negotiated with the qualified contractor that mitigated lost schedule time and avoided contract liquidated damages. GCS also provided on-site administration to expedite decisions and monitor cost.